Main stages of repair works in the apartment

Main stages of repair works in the apartment.

How to start repair works of the apartment?

The first stage of the repair of old houses is the damage and dismantling firstly of the dilapidated walls and partition walls, getting rid of the wall and ceiling finishing. This phase is among the most "unclean" stages of the repair work.

One more amongst the most crucial and "dirty" works is the window block replacement. It is essential to do this first off because dirt and dust will be unallowable during following phases and it is forbidden at all to open windows during painting and wallpaper works (large drops of the temperature and moisture are unallowable). After mounting windows and windowsills it is required to load them right away in polyethylene film and to cover windowsills in addition by the fiberboard (in order to avoid scratches).

The following stage is electrical wiring. Wiring can be installed in walls or along the flooring. Circuitry is made inside the pipelines to ensure electrical security and boost reliability. The pipeline safeguards electrical wiring from external damages and enables to replace the wire entirely without breaking walls and floor just by inserting the new wire rather of the old one.

House Painting follows the circuitry. The regular error during the simultaneous conducting of such works takes place when employees forget to lay out one of the cable televisions and house painters have already plastered and ravelled the wall. As a result, extra works are required to seal chases on the completed wall. The locations of the feed switch and wall outlet area and their number must be thought-out in advance. The scheme of power circuitry is typically included into the design project.

Later on the system should be ready to service in case of failures. In addition to the circuitries, the telephone cable and the television cable are set out. The power cable need to not be laid out near the telephone and antenna cable televisions to prevent noise pickup and interference. The most peculiar moment is setting out the TV cable television. In order to make 2 (or 3) TV sets in the apartment or condo the 2nd cable is typically merely "securely soldered" in parallel, so the cable resistance is decreased. As a result, the screen quality is deteriorated, numerous programs can't be received and etc. In order to avoid such scenario it is required to welcome a specialist with special devices. He will measure the signal level of the each TV-feeder and install TV-amplifiers or TV-filters.

Painting is the most long-term process, that is why it is performed at the same time in all properties, if it is possible. Hold-ups are linked with the innovation. Each applied layer of the plaster (or filling out completing) should dry completely before the work will continue.

Works in hygienic arrangements and the cooking area start simultaneously with house painting. It is better to fulfill so-called "dirty" works in the first place and concurrently. In accordance with the strategy of the hygienic specialist place welding, wall chasing and pipeline run are performed. Steam radiator admissions are prepared, taps and brackets are mounted, however radiators are not installed.

Then operates in hygienic arrangements are conducted according to the strategy. The bath is installed, then walls are smoothed out and the tile is laid on walls. The following stage is assembling ceiling and laying tiles on the flooring. And at last other hygienic devices, mixers and accessories are mounted.

After electrical wiring, setup of rosette plates and terminal boxes the voltage is signed in all point. Ends of electrical wiring are insulated and laid out into rosette plates. Sockets and breakers are not set up during this stage in order to conserve their surface look. The surface puttying of walls is conducted all at once. The technologically precise control of drying of the layer of the plaster (filling) is carried out by drymeter. It is a special instrument that measures wetness of the material.

The following stage is the procedure of fill. Fill can be made with various materials-- from typical masonry cement-sand mixture to self-aligning floorings. The benefit of the simple mix is its cheapness, the drawback is that such mix is much harder aligned at the level and the final dry time of such fill is 40 days, just then the next stage of the deal with floor can be carried out, i.e. the period is too long. Self-leveling self-aligning floorings are much more expensive, however more technological. Lining up takes place nearly "instantly" i.e. fluid service of mixture is put out, then it runs and you receive the horizontal surface. The last dry time is 15 days i.e. you have considerable time economy. The system "warm floor" is set up into the fill. If the so-called "wet procedures" are inapplicable the technology of the dry lining up (the fill innovation) is used bases for floorings with adjustable flooring battens are mounted.

After fill door boxes and door are set up. Installation of doors need to take into the account density of future flooring covering. After installation the door can be removed its hinges and eliminated until the end of repair or loaded into polyethylene film to secure from damages. At plumber nearby services the same time ceiling can be painted and the tile can be laid in that facilities where it was prepared. The tile needs to be laid on the definitely dry overlay.

Finishing of the floor mounting depends on the prepared covering. For the most part (if finish covering is not the tile) fill is covered by bitumen mastic and plywood sheets are laid. They are fixed to the floor by self-tapping screws. One plywood sheet is repaired by 30-50 self-tapping screws to offer the close repairing of plywood and long-lasting service of the flooring without squeak and bulging. The plywood provides the additional heat- and acoustic insulation. After installing of the plywood is finished, wallpaper for painting can be pasted on walls.

image

In properties where finish covering of the flooring is laminated floor covering or parquet hoard, the common wallpapers are pasted (not for painting) in the very Fix-It Right Plumbing first place. Then the floor covering is mounted.

If surface covering of the flooring is the block parquet, the parquet is laid in the first place, then it is scraped and covered by one layer of lacquer. After this the common wall-papers are pasted and the parquet is covered by the rest layers of lacquer (depending upon the quality of the parquet and lacquer). The mentioned consequence is linked just with such rushing process when the excellent quantity of dust is developed. In spite of the reality that good floor mills are geared up with the vacuum, the sufficient amount of dust is sped up on surrounding topics consisting of walls. Dust is very acerbic and is badly washed off. That is why in order not to harm wallpapers, they are pasted after scrambling and in order the parquet do not soak up the surplus moisture it is covered by the one layer of lacquer before wallpaper pasting.

After this the main works can be considered to be completed. It is left just to install the plinths, decorative components, breakers and sockets, curtain holders, to hang doors, plant-bands and others.

In conclusion it is required to keep in mind that the series of works was listed in general and can change depending upon the guaranteed circumstance-- the number of spaces in facility, your resources, peculiarities of the construction of the multilevel facilities. It is based on common sense and everyone efficient in analysis can independently develop such a sequence.